8/5/2019 - Road Work Report for Week of August 5, 2019

Roads to be Chip Sealed in August:

Work expected to be completed within two weeks. Schedule subject to change due to weather and contractor availability.

  • Ballantine Park
  • Beecher Drive
  • Berkshire Road
  • Crook Horn Road (Roxbury Road into Settlers Park)
  • Housatonic Trail
  • Mansion House Road
  • Old Poverty Road
  • Pascoe Drive
  • Short Rock Road
  • Sylvan Crest Drive
  • Westenhook Terrace

Mill and Pave projects tentatively scheduled for September:

  • Cedar Crest Drive
  • Georges Hill Road (from just South of Laurelwood Lane to just south of Cooper Hill Road)
  • Lakeside Road (Georges Hill Road to Fish Rock Road)
  • Parking lots within the town complex (Town Hall lower lot, Fire Dept. upper lot, Police lot)

Road Reconstruction scheduled for September:

  • Hickory Lane

Tree Removal in preparation for Road Reconstruction:

  • Hollow Swamp Road

Catch Basin Repair as scheduling allows:

  • Heritage Road (Pomperaug River Bridge to Bates Rock Road)
  • East Hill Road (Old Poverty Road to Fairway Drive)

Spot Paving this fall:

  • Cedar Trail
  • Midland Trail
  • Spring Trail