7/20/2020 - Road Work Report for the Week of July 20, 2020

Paving:

Plaster House Road (Culvert Project) to begin July 21.

Chip Sealing:

Scheduled to begin week of July 27.

  • Horse Fence Hill Road
  • Oakdale Road
  • Manor Road
  • Poplar Drive
  • White Birch Lane
  • Hillside Road
  • Main Street South (Rt. 172 to Fish Rock Road)
  • Fish Rock Road (Ichabod Road to River Road)
  • River Road (Fish Rock to Glen Road)
  • South Flat Hill Road (paved section)

Reclaiming and Paving:

Pine Rock Road to begin week of August 10.

 

Please note: schedules subject to change due to weather conditions and scheduling with outside vendors.